DERBYSHIRE CONSERVATION VOLUNTEERS

TASK REPORT

Site:

New House Farm, Kniveton

Total Workdays:

8.5

Work Done For:

Bob Smail

Date:

30th March 2003

WORK REPORT:

Slip planting a variety of trees and dimantling and repairing a drystone wall

The damaged wall that we worked on last time was revisited in order to finish it off. Then we moved on to a new section, shown here.

The new section of wall at the top end was finished at the end of this glorious day. Notice the left over stones!

Volunteers on task:

Tools Used:

Chris, Stuart, Jane, Peter T, Katheryn, Wendy, Martin, Sandra, Geraldine/Ellie 1/2

Spade, Walling hammer

Drivers:

Chris, Geraldine

Total Volunteers:

10

Mileage:

42

Task Report List

Back to Main Page